Custom Build

PIP in Madeira: How to Obtain the Câmara's Written Opinion

8 min read
The Short Answer A PIP (pedido de informação prévia) asks the Câmara Municipal (the municipal council) to rule formally, and in writing, on a specific operation before you commit to a purchase. A favourable answer binds the authorities in the decision that follows, within the elements and conditions stated, and you then have two years from notification to take the next step (RJUE, articles 14 to 17). Only a complete detailed PIP can exempt the operation from a licence or a prior notice (comunicação prévia). The more precisely the request is framed, the more useful the answer.

“The Câmara told me we could probably build. Can I have that answer in writing, with legal value?” If you are about to pay a deposit on a plot or a ruin, the difference between information given at the counter and a formal decision can shape what you commit to.

What a PIP is and what it asks of the Câmara

The pedido de informação prévia, or PIP, is the request you file for the Câmara Municipal to rule on a specific operation. You can use it to examine a new build, the reconstruction of a building or a conversion. The quality of the answer depends partly on how precisely you frame the request. “Is a house conceivable here?” and “can this house, of this floor area, at this location be built?” do not fix the same scope of decision.

Two ways to file the request

Articles 14 to 17 of the RJUE, approved by Decreto-Lei n.º 555/99, set the framework for the PIP. The reform introduced by Decreto-Lei n.º 108/2026 has applied since 1 October 2026, subject to transitional provisions and to Madeira’s own adaptations (what the 2026 reform changes in practice). Check which regime applies if you are picking up a file lodged before that date. RJUE, articles 14 to 17 · Adaptation of the RJUE to Madeira

The PIP under article 14, n.º 1 concerns the feasibility and conditions of the operation. It lets the Câmara examine uses, easements, infrastructure and siting parameters. For agricultural land, for example, ask whether a single-storey dwelling is admissible on the southern part and which setbacks or access constraints apply. The answer can help you decide whether the price justifies a more detailed study.

The PIP under article 14, n.º 2 allows a more defined project to be assessed. Depending on the operation, it describes in particular the siting, volume, floor areas, uses and infrastructure. The preparatory work is heavier. It becomes relevant when you need the Câmara to examine a precise footprint, a change of use or an access solution before you buy.

To choose, ask the architect which uncertainty the file must resolve. If you do not know the status of a ruin, start by searching the archives and measuring what exists. If the seller hands you plans, reconcile them with the plot and its actual condition before using them for a PIP.

Can a buyer file a PIP without owning the land?

Yes. Article 14 allows any interested person to file a request. If the applicant is not the owner, the file must identify the owner and the holders of other real rights by means of a land registry certidão. The Câmara notifies them of the opening of the procedure under the applicable regime. RJUE, article 14

To organise the process, ask the seller for the certidão permanente predial code, the caderneta predial, earlier municipal files and permission to carry out a survey on site. The right to approach the Câmara does not on its own give you access to private land or to the documents the seller keeps. If the land belongs to several people, have someone check who can give the necessary authorisations and, later, sign the CPCV (contrato-promessa de compra e venda, the promissory purchase contract). This is part of the independent due diligence that comes before any commitment.

Documents, timelines and cost of the PIP

Portaria n.º 320/2026/1 of 31 July provides the templates and supporting documents for the new procedures. To prepare the meeting with the architect, gather the property references, the location plan, the plot boundary, photographs and a note describing the operation. Depending on the PIP, plan for a topographic survey, plans, sections, the projected floor areas and a description of the networks or the access. For a ruin, also document the existing volumes and the use to be converted. Portaria n.º 320/2026/1

Article 16 sets maximum decision periods of 15 days for the n.º 1 PIP, 30 days for ordinary operations under n.º 2 and 45 days for a subdivision requested under n.º 2. The legal starting point is the expiry of the period set for the preliminary examination of the file (saneamento e apreciação liminar). Where external consultations are needed, the period runs from receipt of the last opinion or from the expiry of the period for issuing it, whichever comes first. For a particularly complex detailed PIP, an exceptional extension is possible once, for a period equal to the initial one, by reasoned and notified decision. Also allow time to prepare the documents and obtain the seller’s papers. RJUE, article 16

The cost combines the municipal fee and, depending on the file, architect and surveyor fees. The tariff depends on the municipality and the type of operation. In São Vicente, ask for the relevant line in the Taxas Urbanísticas schedule, then for a quote that separates the initial study from the preparation of the PIP. As a benchmark for one item in the file, a certidão permanente ordered online costs €15. That sum covers the land registry document only. São Vicente, Taxas Urbanísticas · Registo Predial Online

What a favourable answer commits for two years

Under article 17, a favourable answer on a PIP under n.º 1 binds the competent authorities in the decision on the licence application that follows, or in the control of an operation subject to comunicação prévia. The effect applies to the project examined, within the limits of the elements and conditions stated in the decision.

A favourable PIP under n.º 2 that contains all the applicable elements of points a) to f) of article 14 can exempt the operation from a licence or a comunicação prévia, and from fresh external consultations. The project must be carried out exactly in the terms assessed. Ask the architect to confirm that the decision covers every relevant element and to list the formalities that remain before work starts. Read the external opinions annexed to the decision as well. RJUE, article 17

The period is two years from notification of the favourable decision or from the formation of a deferimento tácito (tacit approval of the request under the conditions set by law). Depending on the case, you must file the licence application or the comunicação prévia that follows, or start the operation covered by the detailed PIP that meets the exemption conditions. After expiry, article 17 also provides for a single request to confirm that the factual and legal conditions still hold. The president of the Câmara then has 20 days to rule. If the conditions are confirmed, or if the law attaches an effect to silence when that period expires, the applicant has one year to complete the relevant step. Have the dates and documents checked before relying on a tacit acceptance. RJUE, article 17, n.os 5 to 7

What this means for a buyer in Madeira

When the sale depends on feasibility, request the PIP before the CPCV if the seller agrees to wait. If you sign the promise during the procedure, ask your lawyer to draft a condition precedent that specifies the required outcome. For example, the file may target a dwelling of a minimum floor area, with a defined access. Specify the deadline, how a decision carrying costly conditions is treated, any extensions and the refund of the sinal (deposit paid as a guarantee when the promise contract is signed) if the condition fails. For the wider sequence of buying a plot and building on it, see the guide to buying land and building a house in Madeira.

If the seller presents their own PIP, ask for the full decision, its annexes and proof of notification. Where the holder changes, article 16, n.º 10 provides that the new holder proves this to the Câmara so that the change can be registered. Have it confirmed that the period is still running and that your project can reuse the approved parameters. A PIP favourable to rebuilding a 40 m² building deserves a fresh analysis if you intend to buy in order to create two dwellings or enlarge the floor area.

Madeira Compass can coordinate the review of the plot, the preparation of the questions for the Câmara and the exchange with your lawyer before the CPCV, through its custom build advisory. A sound purchase decision takes into account both the municipal outcome and what its conditions will cost you. More answers on planning and permits are collected in the FAQ.

This article provides general information and is not legal advice. The rules cited are stated as at November 2026 and may change. For a purchase or project where the PIP is decisive, engage a qualified Portuguese lawyer and an architect before acting.

Frequently asked questions

Can I request a PIP without having signed the CPCV?

Yes. You can file as an interested person, with the required land registry information. Arrange with the seller access to the site and to the documents you need.

Does a favourable PIP replace a building permit?

A simple PIP binds the decision or the control that follows. A complete detailed PIP can exempt the approved operation from a licence or a comunicação prévia, on the conditions of article 17.

How long does a PIP take in Madeira?

Article 16 provides for 15, 30 or 45 days depending on the procedure, with starting points specific to each file. Add the survey, the preparation of the plans and any consultations to your purchase timetable.

How long does a favourable PIP remain valid?

In principle you have two years to complete the required step. A single procedure to confirm that the conditions still hold can open an additional period of one year under article 17.

What happens to my deposit if the PIP is unfavourable?

The fate of the sinal depends on the CPCV. Have the refund conditions written in, along with how a favourable answer that covers only part of your project is treated.

Buying or building in Madeira?

Begin a private conversation

5.0 5 Google reviews Verified on Google ↗

About Madeira Compass Written by the Madeira Compass advisory team, independent advisors with deep roots in Madeira's property market, built through years of on-the-ground acquisition, construction, and relocation mandates on the island. Fee-only. Retained by the client. No commission from any vendor or institution. Learn about our approach →